Data center developers are looking for large pieces of Texas land with power, fiber and room to build. If you own acreage, this guide explains what they look for, how much land a project needs, and what an option, lease or sale can look like, in plain English. It is written by Davis Vernon's Land & Energy Advisory team in Vernon, Texas. Last updated: November 2026.

Own land and want a straight answer? Tell us about your land. Looking for sites? See off-market sites.

Can My Land Host A Data Center?

Maybe, and it depends on much more than acreage. Developers screen land against the factors below. Power usually decides it: a parcel with a realistic path to power is worth a serious look, and a parcel without one rarely gets far, no matter how big it is.

Power

The deciding factor. Developers look for land close to high-voltage transmission lines and substations, and a utility that can actually serve tens or hundreds of megawatts. A nearby line is not the same as available capacity.

Fiber

Data centers need high-capacity fiber routes. Land near existing long-haul or metro fiber is far easier to serve than a site that needs miles of new build.

Water and cooling

Cooling design drives water demand. Developers check local groundwater rules, municipal supply and whether air-cooled or low-water designs are an option.

Natural gas

Some projects plan on-site generation, so a nearby gas pipeline with spare capacity can add real value.

Size and shape

Large, contiguous, usable acreage matters more than gross acres. A square, flat 300 acres beats a stretched, broken 500.

Flood and terrain

Floodplain, wetlands, creeks, steep ground and pipeline or power-line easements all subtract from buildable land. The calculator below shows how much.

Zoning and access

Developers check county and city rules, road access for heavy trucks, and whether neighbors or local officials are likely to object.

Title and minerals

In Texas the minerals are often owned separately from the surface. A severed mineral estate, liens or unclear title can slow or stop a deal.

Environmental

Expect a Phase I environmental review. Past oil and gas activity, old dumps or storage tanks are common findings on rural land.

Being near a power line is not the same as having power available. The utility has to confirm capacity, and large connections can take years. Confirm before you assume.

Planning Calculators

Three quick tools for early planning. They run in your browser, store nothing and ask for no contact information. They give rough ranges only. Real needs depend on building design, substation size, cooling, setbacks and the utility.

1. How Much Land Does A Power Load Need?

Enter the planned load in megawatts (MW) to see a rough acreage range.

Worked example: a 100 MW hyperscale project at 1 to 2 acres per MW needs about 100 to 200 acres (0.2 to 0.3 square miles).

Planning ranges used: gross acres per MW, including buffers and an on-site substation
Project typeAcres per MW
Edge / small site (up to 10 MW)1 to 3
Colocation (10 to 50 MW)1 to 2
Hyperscale (50 to 300 MW)1 to 2
AI / gigawatt-scale campus (300 MW and up)1 to 2

2. How Much Of My Parcel Is Buildable?

Gross acres are not buildable acres. Enter the acres lost to each constraint. If some acres fall in more than one (for example a setback inside a floodplain), enter them under overlap so they are not subtracted twice.

Worked example: a 500 acre parcel with 40 acres of floodplain, 20 of wetlands, 30 of steep ground, 15 of easements and 60 of setbacks, less 25 acres of overlap, leaves about 360 buildable acres (72%). At the hyperscale range that could support roughly 180 to 360 MW. This does not check whether the buildable land is in one connected piece, which matters a lot.

3. What Could An Option Agreement Pay Me?

Options pay a yearly fee for the right to buy your land later. Enter the terms you have been offered, or try some, to see the totals. Fees are assumed to be non-refundable.

Worked example: 300 acres at $30,000 per acre ($9,000,000), a $500 per acre yearly fee, a 2 year initial term and two 1 year extensions with a 10% fee increase each time. If the buyer walks after the initial term you keep $300,000. If they use every extension and then walk you keep $646,500. If they close after the last extension with fees credited, you receive $9,000,000 in total.

Got real numbers for your land? Send us the county and acreage and we'll give you a straight read on whether it looks like a candidate.
Check My Land →

These calculators are for early planning only. They are not an appraisal, engineering study, offer, or legal, tax or financial advice. Talk to us about your actual land.

Red Flags That Can Stop A Site

These are the issues that most often kill or delay a data center deal on rural land. Knowing them early saves time:

  • No realistic path to power: the nearest substation is far away or the utility has no capacity.
  • Most of the parcel is floodplain, wetlands, creek bottom or steep ground.
  • Several small tracts with different owners that would have to be assembled.
  • Severed minerals with no surface use agreement in place.
  • Pipeline or transmission easements running through the middle of the buildable area.
  • Poor road access, or a long haul over county roads that can't carry heavy loads.
  • Local opposition, restrictive zoning or a moratorium on large projects.
  • Title problems, unresolved heirship or liens.
  • Limits on groundwater use in the area.

Things To Weigh Before You Say Yes

Data centers are a debated subject in Texas, and reasonable landowners come down in different places. Before you decide, think about the points below. This is not a case for or against data centers. It is a list of what an owner should understand first.

Water

Cooling design drives how much water a facility uses. Some designs use little water but more electricity. Ask where the water would come from, how much is needed, and what it could mean for your own wells and your neighbors'. Groundwater rules vary by local district.

Power and the grid

A large new load affects utility planning. Ask who pays for new lines and substations, and how the project could affect other customers. Rules in Texas are still changing, so get the current picture from the developer and the utility.

Noise, lights and traffic

Cooling equipment and backup generators can be loud, and construction brings heavy truck traffic. Ask about setbacks, noise limits and buffers between the facility and your remaining land and neighbors.

Neighbors and community

Local reaction can make or break a project. Talk with neighbors and county officials early. Opposition can delay or end a deal, and it can affect relationships long after it is over.

Taxes and incentives

Projects may seek local tax abatements, which is often debated. Changing how land is used can also affect its agricultural valuation, and back taxes may apply. Ask a tax professional before you sign.

Jobs and long-term use

Construction creates temporary jobs, while permanent staffing is usually small compared with the size of the project. Land can be committed for decades, so look closely at term, restoration and decommissioning terms.

What you give up

Farming or ranching use, open land, access and sometimes minerals or other rights. Think about what is left of the rest of your property and how it will be used and reached.

Saying no is a valid answer

Many landowners decide a data center is not right for them, and some keep the land or sell to a farmer or rancher instead. Nothing obliges you to say yes to an offer, and a good advisor will tell you when a deal does not fit your goals.

How Deals Usually Work

Most data center land deals take one of three forms:

Option agreement

What it is: A buyer pays you a yearly fee for the exclusive right to buy your land at an agreed price while they study power, permits and design.

Keep in mind: You keep the land and keep the fees even if the buyer walks away. Check whether fees are credited toward the price and what happens if the buyer asks for extensions.

Land lease

What it is: You keep ownership and are paid rent, usually per acre per year, often with scheduled increases.

Keep in mind: Steady income and you keep the land, but your use of it is limited for decades. Pay close attention to term, restoration and who owns the improvements.

Outright sale

What it is: You sell the land at a negotiated price, often after an option period.

Keep in mind: A clean exit and a known price. Consider the tax effect and whether you want to keep the minerals or other rights.

Always have an attorney and tax advisor review any agreement. Our Land & Energy Guide covers leases, easements and evaluating offers in more detail.

How We Help

  1. Tell us about the land. County, approximate acres, and anything you know about nearby power lines, substations, pipelines, floodplain or minerals.
  2. We screen it. We review the parcel against the factors above and tell you plainly whether it looks like a candidate, and what would need to be true for it to work.
  3. Talk through your options. Option, lease or sale, and what each could mean for you. We point you to an attorney and tax advisor for the legal and tax side.
  4. Take it to the market, or review an offer. Where it fits, we introduce the site to developers and buyers we work with, or help you evaluate an offer that has already reached you.

Davis Vernon has sold Texas ranches and farmland since our founding, and our Land & Energy Advisory practice applies that land knowledge to energy and data center projects.

Off-Market Sites, And Developers Looking For Land

Not every site is publicly listed. We work with landowners on off-market land, including parcels that look like strong candidates for data center and other large-load projects.

If you are a developer or land buyer looking for sites, tell us what you need: the load in megawatts, an acreage range, the region or utility, the timeline and any must-haves such as fiber, gas or water. We will tell you whether we have a match.

Send Us Your Requirements

Frequently Asked Questions

Can my land host a data center?

Possibly, but it depends on far more than acreage. The biggest factor is power: how close the land is to high-voltage lines and substations and whether the utility can serve a large load. Fiber, water, size and shape, flood and terrain, zoning, minerals and title all matter too. The checklist above shows what developers look at.

Does being near a power line mean my land qualifies?

No. Transmission lines carry a limited amount of power, and a data center may need tens or hundreds of megawatts. The utility and the grid operator have to confirm capacity and approve the connection, and large-load requests can take years. Always confirm capacity with the utility before assuming a site has power.

How many acres does a data center need?

It depends on the size of the power load. As a rough planning range, about 1 to 3 acres per megawatt for small sites and 1 to 2 acres per megawatt for larger campuses, including buffers and an on-site substation. A 100 megawatt project might need 100 to 200 acres. Use the calculator above for your numbers.

What is powered land?

Land that has confirmed utility power capacity, or a credible studied path to it. Developers often pay more for powered land because power is usually the longest and hardest part of a project.

What is my land worth to a data center developer?

There is no standard number. Value depends on power availability, location, size, shape, fiber, water, zoning and deal structure. Land with a real power path can be worth more than the same land in farm or ranch use, but that is never guaranteed. A broker opinion and a full read of any offer is the best way to find out.

Is it a good idea to lease or sell my land for a data center?

It depends on your goals, your land and the terms. Data centers are debated in Texas, with concerns about water, power, noise, taxes and local impact on one side and landowner income and demand for land on the other. Understand the downsides as well as the offer, talk to your neighbors and professionals, and know that saying no is a legitimate choice.

Should I sign an option, a lease or sell?

Each fits a different goal. An option pays you to hold the land while the buyer studies it, a lease keeps ownership with you and pays rent, and a sale is a clean exit. Have an attorney and a tax advisor review any agreement before you sign.

What does "fees credited toward the price" mean?

In some options, the yearly option fees you receive are subtracted from the purchase price at closing, so the total you receive does not exceed the price. In others the fees are on top of the price. The option payment calculator above shows both.

What about my mineral rights and groundwater?

In Texas the mineral estate is often owned separately from the surface, so a surface use agreement or other arrangement may be needed. Groundwater is generally regulated locally by groundwater conservation districts. Both can affect a data center site, so find out what you own and what is severed before you talk price.

A developer or land agent contacted me. What should I do?

Be cautious about signing anything quickly, especially non-disclosure agreements, exclusivity or option agreements. Ask who the end user is and what the real terms are, and have an attorney review them. Our team can help you evaluate the offer.

How long does a data center land deal take?

Often many months and sometimes years. Securing power usually takes the longest, which is why options with extension periods are common.

How does Davis Vernon help landowners?

We help you understand whether your land looks like a candidate, explain your options, and where it fits connect the site with developers and buyers or help you evaluate an offer. We also work with off-market sites. Start with a conversation, with no obligation.

Glossary

MW (megawatt)
A unit of power. Data center size is usually described by the megawatts of electricity it uses.
kV (kilovolt)
A unit of voltage. High-voltage transmission lines are typically 69 kV and higher, and larger ones carry far more power.
Substation
A facility that steps voltage up or down. Large data centers often need a new or expanded substation.
Transmission line
A high-voltage line that moves power over long distances, as opposed to the smaller distribution lines that serve homes and farms.
Interconnection
The utility's process and approval for connecting a large new load, or generator, to the grid.
Powered land
Land with confirmed utility power capacity, or a credible studied path to it.
ERCOT
The grid operator for most of Texas. Some parts of the state, such as portions of the Panhandle, are served by other grid operators.
Behind-the-meter
Power generated on site, such as from natural gas, that serves the facility directly rather than coming from the grid.
Option agreement
A contract paying the landowner for the exclusive right to buy the land at a set price during a set period.
Easement
A right for someone else to use part of your land for a specific purpose, such as a pipeline or power line.
Surface use agreement
An agreement covering how the owner of the minerals may use the surface of the land.
Floodplain
Land that is at risk of flooding, typically shown on FEMA flood maps. It is difficult to build on.
Phase I ESA
A Phase I Environmental Site Assessment, a standard review of a property's environmental history.
ALTA survey
A detailed land survey to a national standard, often required by lenders and buyers for large deals.
Due diligence
The period when a buyer investigates a property before committing to buy.
Land assembly
Combining several parcels, often from different owners, into one large site.
This guide is general information, not legal, tax, engineering or financial advice. Every property and deal is different. Confirm power and other facts with the utility, and have professionals review any agreement before you sign.